Service for Spring Break Residents
Residents of La Plata, Pyon-Chen, Johnson-Whittle and the South Campus Residence Halls should continue to request work and report issues by calling the Service Center at 301-314-9675. Residential Facilities staff will respond to emergency and critical work requests throughout the break period.
Some Residential Facilities staff may schedule inspections within student rooms to identify work and projects needed next summer.
Across campus, Residential Facilities staff will also respond to service requests reported by residents prior to the break that are not yet completed. When staff enter resident spaces, they will leave notices or copies of service requests describing what was done.
Residents of La Plata, Pyon-Chen, Johnson-Whittle and the South Campus traditional-style residence halls will receive regular housekeeping services to the community bathrooms and public areas daily (Monday, Wednesday through Friday).
Special Projects
In addition to those routine items listed above, we are planning the following special projects over the break. The dates listed below are planned, but subject to change due to changes to the University operating schedule, inclement weather or other maintenance priorities.
Cambridge Community
Bel Air, Cambridge, Centreville, Chestertown and Cumberland halls
| Building | Dates | Times | Project Description |
|---|---|---|---|
| Cambridge | March 16–March 27, 2026 | 9 a.m. to 4 p.m. | Jetting exterior storm drains/sewer drains. |
| Centreville | March 16–March 20, 2026 | 6 a.m. to 4 p.m. | Elevator Modernization, Car #3 is out of service. |
| Cumberland | March 16–March 20, 2026 | 6 a.m. to 4 p.m. | Elevator Modernization, Car #2 is out of service. |
Denton Community
Denton, Easton and Elkton halls
| Building | Dates | Times | Project Description |
|---|---|---|---|
| Denton | March 16, 2026 | 6 a.m. to 3 p.m. | Perform preventative maintenance on the building's electrical infrastructure. Electrical outage for the entire building. |
| Denton | March 20, 2026 | 8 a.m. to 4 p.m. | Tree pruning in the Denton Community. |
| Elkton | March 16, 2026 | 6 a.m. to 3 p.m. | Perform preventative maintenance on the building's electrical infrastructure. Electrical outage for the entire building. |
Ellicott Community
Ellicott, Hagerstown and La Plata halls
| Building | Dates | Times | Project Description |
|---|---|---|---|
| Ellicott | March 16–March 20, 2026 | 7 a.m. to 3 p.m. | Remove one window and mock up the proposed new window. Installation of the new window saddle type heat pump unit on the lounge 2123. The immediate area will be contained & monitored. |
Heritage Community
Pyon-Chen and Johnson-Whittle halls
| Building | Dates | Times | Project Description |
|---|---|---|---|
| Johnson-Whittle | March 16–March 20, 2026 | 7:30 a.m. to 3 p.m. | Repair the following shower enclosures: 6228, 6221, 6125, 6124, 6123, 5224, 5119, 5118, 4221, 3124, 4228, 2224. These bathrooms will be offline 24 hours after the work is complete. Students should utilize other available bathrooms. |
| Pyon-Chen | March 16–March 20, 2026 | 7:30 a.m. to 3 p.m. | Repair the following shower enclosures: 3130 and 3225 . These bathrooms will be offline 24 hours after the work is complete. Students should utilize other available bathrooms. |
Oakland Community
Oakland Hall
| Building | Dates | Times | Project Description |
|---|---|---|---|
| Oakland | March 16–March 20, 2026 | 9 a.m. to 4 p.m. | Walkthrough of the building (corridors only) in preparation for a summer project (FCU Controllers). |
North Hill Community
Anne Arundel, Caroline, Carroll, Dorchester, Prince Frederick, Queen Anne's, St. Mary's, Somerset, Wicomico and Worcester halls
| Building | Dates | Times | Project Description |
|---|---|---|---|
| Anne Arundel | March 18–March 20, 2026 | 7:30 a.m. to 3:45 p.m. | Thoroughly clean the bathrooms, stairs, and floor. |
| Caroline | March 16–March 27, 2026 | 9 a.m. to 4 p.m. | Jetting exterior storm drains/sewer drains. |
| Caroline | March 18–March 20, 2026 | 7:30 a.m. to 3:45 p.m. | Thoroughly clean the bathrooms, stairs, and floor. |
| Carroll | March 18–March 20, 2026 | 7:30 a.m. to 3:45 p.m. | Thoroughly clean the bathrooms, stairs, and floor. |
| Dorchester | March 18–March 20, 2026 | 7:30 a.m. to 3:45 p.m. | Thoroughly clean the bathrooms, stairs, and floor. |
| Prince Frederick | March 18–March 20, 2026 | 7:30 a.m. to 3:45 p.m. | Thoroughly clean the bathrooms, stairs, and floor. |
| Queen Anne's | March 18–March 20, 2026 | 7:30 a.m. to 3:45 p.m. | Thoroughly clean the bathrooms, stairs, and floor. |
| Queen Anne's | March 20, 2026 | 9 a.m. to noon | Control stop replacement in bathroom 3101. Hot water outage for the entire building 9 a.m. to noon. |
| Somerset | March 18–March 20, 2026 | 7:30 a.m. to 3:45 p.m. | Thoroughly clean the bathrooms, stairs, and floor. |
| St. Mary's | March 18–March 20, 2026 | 7:30 a.m. to 3:45 p.m. | Thoroughly clean the bathrooms, stairs, and floor. |
| Wicomico | March 18–March 20, 2026 | 7:30 a.m. to 3:45 p.m. | Thoroughly clean the bathrooms, stairs, and floor. |
| Worcester | March 18–March 20, 2026 | 7:30 a.m. to 3:45 p.m. | Thoroughly clean the bathrooms, stairs, and floor. |
South Hill Community
Allegany, Baltimore, Calvert, Cecil, Charles, Frederick, Garrett, Harford, Howard, Kent, Montgomery, Prince George's, Talbot and Washington halls
| Building | Dates | Times | Project Description |
|---|---|---|---|
| Allegany | March 19, 2026 | 9 a.m. to noon | Angle stop replacement in unit 0106 bathroom. Domestic Hot/water Outage entire building 9 a.m. to 12 p.m. Students should remove any items from under bathroom sinks. |
| Allegany | March 16–March 27, 2026 | 9 a.m. to 4 p.m. | Jetting exterior storm drains/sewer drains. |
| Allegany | March 16–March 27, 2026 | 9 a.m. to 5 p.m. | Replacement of brick staircases at north side of building at entry doors at entry doors NE1195A and NE1197A. Entering the following suties/apts: 1109, 1111, 2109, 2111, 3111,1113, 1115, 2113, 2115, 3115. Students should open the exterior door slowly when exiting the building and use caution when entering or exiting the building through doors NE1195A and NE1197A |
| Baltimore | March 16–March 20, 2026 | 9 a.m. to 4 p.m. | Upgrade the expired smoke detectors. Students should clear 3 feet around the smoke detectors. |
| Cecil | March 16–March 20, 2026 | 7 a.m. to 4 p.m. | Measure the windows in all bedrooms. |
| Garrett | March 16–March 20, 2026 | 9 a.m. to 4 p.m. | Upgrade the expired smoke detectors. Students should clear 3 feet around the smoke detectors. |
| Howard | March 16–March 20, 2026 | 9 a.m. to 4 p.m. | Upgrade the expired smoke detectors. Students should clear 3 feet around the smoke detectors. |
| Howard | March 16–March 27, 2026 | 9 a.m. to 4 p.m. | Jetting exterior storm drains/sewer drains. |
| Kent | March 16–March 20, 2026 | 9 a.m. to 4 p.m. | Upgrade the expired smoke detectors. Students should clear 3 feet around the smoke detectors. |
| Montgomery | March 16–March 20, 2026 | 9 a.m. to 4 p.m. | Upgrade the expired smoke detectors. Students should clear 3 feet around the smoke detectors. |
| Montgomery | March 16, 2026 | 6 a.m. to 6 p.m. | Replacement of automatic transfer switch. Electrical outage for the entire building. Student should remove all food from the refrigerators. |
| Prince George's | March 16–March 20, 2026 | 9 a.m. to 4 p.m. | Upgrade the expired smoke detectors. Students should clear 3 feet around the smoke detectors. |
| Washington | March 16–March 27, 2026 | 9 a.m. to 4 p.m. | Jetting exterior storm drains/sewer drains. |